WR boilers

WR boilers manufactured by the Company and culm coal-fired adapted for biomass co-firing are the main source of heat in municipal heating and industrial plants. A series of WR boiler types with outputs from 5 to 40 MW is designed to fully cater for the needs of our clients and meet their expectations.

A typical WR boiler is built in a two-pass system. The first pass is a furnace chamber enclosed by membrane walls. In the second screen pass there is a so-called convective bundles in the water heater. Depending on needs, the boiler can be equipped with an additional water heater placed as a separate block, most often in the so-called third pass.

The WR boilers produced by Energoserwis S.A. Lublin are characterised by very high efficiency and low pollution emission. They constitute a self-supporting structure suitable for construction on the foundations of the old type WR boilers. They are equipped with all kinds of necessary auxiliary installations and a control system and instrumrntation

Kocioł energetyczny WR1
Kocioł energetyczny WR2

OR boilers

OR culm coal-fired boilers produced by Energoserwis S.A. Lublin are used in industrial plants and heat and power stations to produce steam. The range covers boilers with a capacity from 16 to 64 tonnes of steam per hour.

A typical OR boiler is built with a three-pass system. The first pass is an entirely screened furnace chamber, the second pass contains superheaters, while in the third plate-armoured pass there is a water heater. The OR boilers are equipped with a self-supporting  structure, suitable for building on the foundations of WR boilers and the old-type OR boilers.

The OR boilers manufactured by Energoserwis S.A. Lublin are characterised by high process performance over a wide load range and low pollution emission. They are equipped with all necessary auxiliary installations and a control system and instrumrntation.

kocioł energetyczny OR
kocioł energetyczny OR1

Other steam and water boilers

Based on the received documentation as well as its own records, Energoserwis S.A. Lublin modernises water WP boilers and steam boilers of different capacities up to 100 tonnes of steam per hour.

Examples of such boilers include:

  • WP 120 boilers modernized in 2005 – 2006 in EC Siekierki
  • CKTI-75 boilers revitalized (modernized) in the years  2008 – 2011 in Soda Polska Ciech
  • EKM 50 boiler modernized in the years 1998 – 1999 and 2003 – 2004 for EC Megatem Sp. z o.o. w Lublinie
  • Production and assembly of pressure parts for OP-230 and OP-650 boilers